What is an F10 form?

Under the Construction (Design and Management) Regulations 2015 (CDM Regs 2015), when a project is notifiable it is the Client’s duty to submit an F10 form to the HSE.

The only exception to this is where the client is a domestic client.  In these circumstances, the responsibility for notification automatically passes to the contractor (or Principal Contractor where there is more than one).  The Principal Designer can assume the responsibility for notification of a domestic project, but only where there is written agreement between the domestic client and the Principal Designer that they will carry out the client duties.

The term ‘F10’ is simply the name that the HSE has given to this notification form.